What is your single biggest issue when it comes to Maintenance Planning & Scheduling?


Recommended Posts

  • Community Leader

Hi @Fred Ward,

I have been through something similar in the best during small preventive shutdowns. Basically, we took two actions to try to improve this situation:

1- A Shutdown Planning meeting, where we discussed with the production supervisor every single task that would be done on that particular day and by what time we would need it ready for us, including a priorization of tasks, displaying which one should be ready first. After agreeing during the meeting, an email was sent with main topics discussed during the meeting, including the plant release time to everyone, including maintenance and production managers;

2- Making notes of every releasing plant time, especially for those tasks that were delayed due to not having the plant ready for maintenance. Then, another email used to be sent to everyone, including the maintenance and production managers, highlighting everything that went wrong during the shutdown, which includes tasks not completed on time due to plant release delays + by what time it was agreed to be released + actual time released.

Just be careful when sending email with this sort of information to make sure the operators will not feel atacked by the info, but as an impartial way of recording what went wrong.  Trying to understand the reason of not releasing the plant on time and trying to help them out solving these sort of problems when we could might be aa good option.

Hope this helps.

Regards,

Raul Martins

Link to post
Share on other sites
  • Replies 76
  • Created
  • Last Reply

Top Posters In This Topic

Top Posters In This Topic

Popular Posts

Planning maintenance work can be a challenge because it normally consists of two different types of maintenance: Unplanned or emergency maintenance to fix equipment breakdowns or other urgent wo

Hi @ALI, What you describe is a classic problem that people face before they have a robust and stable planning & scheduling process in place. One key step you should take is to get a prioritisatio

Work Load Balancing - Many years ago, I had conducted a study whereby I collected several CMMS databases from various company locations. A macro was created and ran against each DB exporting PM

  • Founder
On 5/5/2020 at 11:36 PM, Fred Ward said:

My biggist problem at the moment is i can plan work but have problems with the permit office releasing plant for us to do the work.

This has been something I have experienced plenty of times, at different plants and in different parts of the world. In all cases the best approach I found was to really get Operations involved in the development of the Frozen Weekly Schedule and then have them present as part of a short, daily meeting where you review the work that was completed yesterday, is due to be completed today and what is scheduled tomorrow (we called it the YTT Meeting with YTT = Yesterday Today Tomorrow). And then at the end of each week report out what works was completed as per the Weekly Schedule and what did not get completed and what the main factors where e.g. extensive permit delays etc. Just as Raul says make sure you stick to data and facts and avoid issues becoming personal.

Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now

×
×
  • Create New...

Important Information

By using this site, you agree to our Terms of Use, Privacy Policy and use of We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue..